Atlas Iron, Wodgina 200 Man Permanent Camp Expansion

MSP News

Friday, 26th January 2012

MSP is pleased to announce that it has been awarded a 200 man camp expansion at the Wodgina Minesite as part of the Atlas Iron expansion project.

The contract has been awarded on a Target Cost Estimate (TCE) basis and long lead items, including the camp buildings and transformers have already been placed.

The project will be delivered concurrently to a 140 man camp expansion at Wodgina which MSP has been engaged to construct by Global Advanced Metals.

Construction works on the 140 man camp has already commenced on site with first building being delivered in mid January 2012.

  
For further information please contact Peter McSweeney
 Email Address: p.mcsweeney@mspengineering.com.au
Telephone: 08 6241 4900.

For printable PDF please click here.

 

Category: MSP News