Project Update - Ta and WHIMS Project

MSP News

The Ta and WHIMS Project at Greenbushes in Western Australia is progressing on schedule with overall completion expected in the 2ndQtr of 2014.

MSP is responsible for the design and construction of the facility under a TCE contract with Talison Lithium Australia Pty Ltd.

The design and procurement component is largely complete as is the site earthworks and civil packages.  Both the SMP and E&I contractors are well advanced with the bulk of the site installation packages.

The overall safety performance of the project has been excellent and once again MSP would like to acknowledge the current safety performance of its contractors.