$7.4M Design and Construct Contract Awarded for Talison Minerals Greenbushes Low Grade Lithium Project

MSP News

The scope of works and deliverables includes engineering, procurement, installation and commissioning of all mechanical and electrical equipment, key structures and civil works, services and spares, in conjunction with the design, programming and implementation of all plant control systems.

MSP previously carried out the project's Scoping Study in late 2007, and in a close partnering arrangement with Talisons has been able to fast track the project to detailed design and construction.

Project completion is expected in February 2009.