Maslin Beach Upgrade Project

/sites/mspaucom//assets/public/image/ProductListing/Maslin-Beach-Photo_LGE.jpg
Role EPC Managers
Client Rocla Quarry Products
Location Rocla’s Golden Grove Quarry South Australia
Product Building Sands & Glass Grade Sands
Project Value $550,000
Scope of Works

MSP Engineering were commissioned by Rocla Quarry Products to investigate the source of coarse sand reporting to their plant thickener.

Following completion of the investigation, MSP was awarded the process, engineering design and construction contract to intercept this coarse material so that Rocla could produce a fine clay material from their thickener underflow, which would be suitable for sale.

In January 2010, MSP successfully completed the upgrade of the Golden Grove Concrete Sands Plant which included modifications to the existing plant structure and the installation of 2 x Minspec Dewatering Screens and 1 x Linatex De-gritting Cyclone Cluster.

Project Achievements MSP delivered the project within the tight budget and project schedule.