OPERATIONS CAMP EXPANSION PROJECT

Client: TALISON MINERALS
Project value: $2.2m
Location: Wodgina, Western Australia

MSP role: Engineering design, procurement and construction of an expansion to an existing operations accommodation camp at Wodgina.

Contract type: GMP contract
Project timing: Construction start 2006, Occupied 2006

MSP was engaged to by Talison Minerals to complete a feasibility study for an expansion of the workers accommodation camp supporting its Wodgina operations, 90km south of Port Hedland.

MSP was subsequently awarded the detailed design and construction contract for the camp expansion, which included new accommodation units, wet mess upgrade, package sewerage treatment facility and other associated infrastructure.

The project was completed within the AU$2.2M GMP contract value with no HSE issues.