SIMBERI GOLD PROJECT

Client: ALLIED GOLD
Project value: $80m project value
Location: Simberi Island, Papua New Guinea

MSP role: Construction manager and Client Representative for the construction of a greenfields gold project in a remote location.

Contract type: CM Services contract
Project timing: Construction start 2008, Commissioning start 2009

MSP was appointed overall project construction manager as well as Client Representative for the Simberi Gold Project located on a remote island in northeast Papua New Guinea.

The project included the design and installation of a 1.6km long rope conveyor system, a 2.0 million tonnes per year capacity carbon-in-pulp gold leaching circuit, together with all associated infrastructure and services, including a service wharf and airstrip.

MSP significantly assisted Allied Gold in achieving all project deliverables, including the management of key engineering and construction subcontractors.

Back to projects